MANU/SC/1512/2022

True Court CopyTM English

IN THE SUPREME COURT OF INDIA

Civil Appeal No. 8571/2022 (Arising out of SLP (C) No. 907 of 2020)

Decided On: 18.11.2022

Appellants: The State of Madhya Pradesh Vs. Respondent: SEW Construction Limited and Ors.

Hon'ble Judges/Coram:
A.S. Bopanna and Pamidighantam Sri Narasimha

JUDGMENT

Pamidighantam Sri Narasimha, J.

1. Leave granted.

2. This appeal is against the decision of the High Court of Madhya Pradesh in an Arbitration Revision No. 4 of 2009 Under Section 19 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 19831 whereby the award of the Arbitral Tribunal was upheld.

3. The short facts leading to the Arbitral Award and thereafter the decision of the High Court may be stated as under.

4. The State issued a tender notice2 for the construction of a Masonry Dam and eventually, Respondent No. 1 (hereinafter referred to as 'the Contractor') was selected as the successful bidder. A contract was entered into on 06.11.1993 for a total consideration of Rs. 1,22,81,86,600/-, to be completed within a period of sixty months.

5. As the only issue arising for consideration, in this case, relates to the claim of escalation made by the Contractor, the relevant Clause is extracted hereunder:

3.11(A) The quoted rates of the contractor shall be inclusive of the leads and lifts and in no case separate payment for leads or lifts to any materials including water shall be payable. Similarly no leads or lifts for the materials issued by the department as prescribed in the tender documents shall be payable. The contractor shall bring approved quality of materials. Different quarries are shown in Annexure C. The details shown in the Annexure C are only as a guide to the contractor but the contractor before tendering should satisfy himself regarding the quantity and quality available and all other details of Annexure C and provide for any variation in respect of leads, lifts, place and method of quarrying, type of rocks to be quarried and all such other aspects in his tendered rate. Later on any claim whatsoever shall not entertained except where any quarry is changed for circumstance beyond the control of contract under the written order of Superintending Engineer in-charge of work.

6. Though the contract was entered into in 1993, the work was suspended for a long time and it resumed on 18.09.2000. While carrying out the construction work under the contract, the Contractor requested an alternate quarry on 07.03.2002, which was denied by the Executive Engineer on 11.03.2002. The decision of the Executive Engineer was also confirmed by the Superintending Engineer on 12.12.2002 and this has led the Contractor to seek a reference of the matter to arbitration3 (hereinafter referred to as 'the first arbitration').

7. While the above-referred claim for an alternative quarry followed by the reference to the arbitration was pending, the Contractor renewed the request for an alternate quarry, this time for excavating sand from Mahuar quarry. This request was made on 20.10.2002. On the basis of this request, a committee of two Execut........