MANU/DE/1590/2020

True Court CopyTM

IN THE HIGH COURT OF DELHI

W.P. (C) 2303/2016

Decided On: 24.08.2020

Appellants: Meera and Ors. Vs. Respondent: MCD and Ors.

Hon'ble Judges/Coram:
Jayant Nath

DECISION

Jayant Nath, J.

1. This writ petition is filed by the petitioners who are the legal heirs of Late Sh. Manish (aged 23 years) who lost his life on 31.08.2014 as a result of alleged gross negligence on the part of officials of respondent No. 1-Municipal Corporation of Delhi (Now, North Delhi Municipal Corporation), Electric Division-I, Kingsway Camp Delhi and respondent No. 2-TATA Power DDL on account of electrocution.

2. The case of the petitioners is that Late Sh. Manish lost his life on 31.08.2014 on account of electrocution when personnel of respondent No. 1 directed the deceased Manish to pull the handle while installing a High Mast Light Pole which was to be electrified by respondent No. 2. The High Mast Light P ole touched a passing unprotected wire maintained by respondent No. 2 on account of which Sh. Manish got an electric shock and fell down on the road. He was taken to BJRM Hospital and later, to Dr. BSA Hospital where he was declared brought dead.

3. It is the case of the petitioners that they have suffered great pain, agony, mental torture and shock due to untimely death of their elder son aged about 23 years. They have also lost love and affection which cannot be compensated in money.

4. The police who were also called registered a FIR bearing FIR No. 503/2014 under section 304A of the Indian Penal Code at P.S. Mahendra Park against the accused persons i.e. officials of respondent No. 1.The petition also points that on 11.08.2015, petitioner No. 1 moved an application calling for a status report from the police officials (The name of the court is not mentioned). A status report was filed by the police. The status report states that as per the statement of the complainant-Sh. Ravinder Kumar, he along with his friends was standing in front of House No. I-2000 when the workers of MCD were installing a High Mast Street Light. Sh. Manish Kumar was also standing there. One person out of the MCD personnel requested Sh. Manish to pull the handle fixed on the pole so that the light could be uplifted. While Manish was following the directions, the circle of High Mast Light touched an overhead cable wire as a result of which Sh. Manish fell down on the road. He was immediately taken to the hospital where he was declared brought dead. An appropriate FIR under Section 304A IP C was registered. Post Mortem report confirms that the cause of death was electrocution. During investigation, the concerned MCD Department on 05.06.2015 gave a reply that the spot was being looked after by a private agency, namely, M/s. Perfect Electric Work on contract basis. Therefore, the report states that a notice was given to M/s. Perfect Electric work. The said Perfect Electric Work provided a copy of the agreement and informed that the contract was from 05.03.2014 for a period of only two months and under the agreement, they have competed that period. The incident is dated 31.08.2014. This report is dated 28.08.2015. It is clear that despite lapse of one year from the incident, the police have been dilly dallying and have not been able to even complete the investigation.

5. A counter-affidavit has been filed by respondent No. 1 on behalf of North Delhi Municipal Corporation. Preliminary objections have been taken including that the petitioners have approached National Human Rights Commission and hence, the writ petition would not lie. It is also pleaded that that there are disputed questions of facts stated in the writ petition which cannot be entertained in the present writ jurisdiction. It is further pleaded that the contract for installing of 4 number Semi High Mast Light Poles was awarded to M/s. Perfect Electric Work on 05.03.2014. It was the M/s. Perfect Electric Work who was working at the site when the mishap occurred. The incident was informed by the site supervi........